Sixareen Building Project - Gallery 1

Shetlopedia - The Shetland Encyclopaedia
Jump to: navigation, search

The pictures on this page are from the 1st stage of the build, in date order. Laying the keel, fixing the stem and stern post, and preparing to fit the first boards, called the Boddam Runners.
A lot of care is taken at this stage to get everything aligned correctly, as any mistakes at this stage will cause problems throughout the build.
Copying something which was built over 100 years ago, is no easy task. And although many of the building techniques are standard to any clinker built vessel, in this case a lot of thought is given to the use of materials, such as Archangel Tar, which would have been used in the original building of Sixareens.

To return to the main Sixareen Building Project page, Click Here.
To view pictures from 14th to 21st February, Click Here
To view pictures from 22nd February to 4th March, Click Here
To view pictures from 5th to 14th March, Click Here
To view pictures from 17th to 31st March, Click Here
To view pictures from 1st to 10th April, Click Here
To view pictures from 11th to 23rd April, Click Here
To view pictures from 24th April to 30th May, Click Here
To view pictures from 2nd to 19th June, Click Here

6th February

Click on any image to enlarge

Oak keel, 20' 2" long, with hog attached lying on starboard side, with stern post and joining skarfs cut.
Keel and hog. Part of hog is cut away to allow the first plank to be attached with copper nails and roves. At each end, the plank will be nailed directly into the hog.
Robbie chisels out rebate in stem to receive the ends of the planks.
The rebate allows the plank ends to fit flush in the stem as in this example of a smaller boat also being built in the boatshed.
Sawn larch waiting to be cut into planks.
Plan of a sixareen for the benefit of visitors. For a better readable version click here
Stem post on the bench, the change of grain lines showing a joint.
Robbie marking the stem, prior to cutting the skarf joint where it will meet the keel.
Starting the angled cut.On the other side of the stem, the cut is as far back as the line near his forefinger.
Nearing the end of the saw cut.
Robbie planing the skarf joint. The angle achieved must match the angle cut on the keel exactly.

7th February

Click on any image to enlarge

Bow, keel and stern post assembled and erected. A string is tied from bow to stern post and plumbobs are hung to check assembly is true.
Stern post and keel skarfed and fixed.
Bow and keel skarf jointed, final section of rebate still to be cut.
Robbie clinks the copper fastening on one side.
Jack holds the heavy hammer on the other side.
Plumbob on centre line of keel which is now firmly fixed to the floor via heavy wood blocks and ready for the next stage.
More braces for the bow.
More support for the stem.
Robbie checks the stem for movement and watches the plumbob.
More supports for the stem and stern are fixed to the shed floor and roof beams.
Jack nails supports to the roof beam.
Named parts of a sixareen.

8th February

Click on any image to enlarge

Temporary guides on the keel, to ensure the correct angle and degree of twist for the first plank on each side.
The four frames (top left) which will dictate the final shape of the hull, will be fixed to the guides.
The glued joint in the stem now through-fastened with copper nails. Planking frames behind.
Jack admiring Robbie Johnson's workmanship in his models of a sixareen and a fourareen.

11th February

Click on any image to enlarge

From a template, the outline of the first board is marked on the larch plank.
Jack cuts the board from the plank.
The board is passed several times through the thicknesser.
Gradually reducing the thickness to the desired 3/4" (19mm).
Robbie planes the bevelled edge on the board.
After several trial fittings and adjustments, the board is just right.
Robbie twists a test piece and decides one hour in the steambox is about right.
With the first board now in the steambox, Jack blocks off the end.

12th February

Click on any image to enlarge Fitting of the first board, the Boddam Runner. (Norwegian: Kjølbord)

The first board is partly nailed and the matching board on the starboard side is tried for size and curvature.
Checking the fit of the board.
The nails holding the first board stick through the cutaway section of the hog.
Half of the skarf joint is cut on the end of the first board.
The first rove is punched on to the protruding nail in the hog.
The excess length is cut off.
Nail tip is clinked on the rove, repeated along the hog.
The degree of twist in the board could not be achieved without the steambox.
Board meets sternpost. At the interface is a layer of syon (a cloth strip) and Archangel tar, in the traditional manner.

13th February

Click on any image to enlarge More work on the Boddam Runner.

Aft section of boddam runner being nailed in place, setting a rove.
Archangel tar oozes from the board/keel rebate.
Board fully nailed and now there is a hint of a boat-shape.
View from forward of the stem. The plywood sheets are kinder to the builders' knees than the concrete floor.
Steam rises from the forward section of the boddam runner as it is tried in place. Malcolm lends a hand.
Tightening up. The clamps are left in place until the wood cools down.
Checking the fit between board and keel.
Board needs a bit off here.
Board sections will be skarfed at the overlap.

To return to the main Sixareen Building Project page, Click Here.
To view pictures from 14th to 21st February, Click Here
To view pictures from 22nd February to 4th March, Click Here
To view pictures from 5th to 14th March, Click Here
To view pictures from 17th to 31st March, Click Here
To view pictures from 1st to 10th April, Click Here
To view pictures from 11th to 23rd April, Click Here
To view pictures from 24th April to 30th May, Click Here
To view pictures from 2nd to 19th June, Click Here